@jaeungkim/gantt-chart

Scheduling

Auto-scheduling, the working calendar, critical path, baselines

You drag one bar two days later and let go. Its successor stays where it was, sitting on top of the task it was supposed to wait for. Every date downstream of that bar is now wrong, and nothing on screen says so. schedulingPolicy decides what happens to the successors when a bar moves.

Auto-scheduling with schedulingPolicy

The prop takes one of three values and defaults to "off".

ValueA successor movesDirectionResult
"off"nevernothing propagates, exactly as if the feature did not exist
"shift-on-overlap"only when the link is brokenlater onlythe successor keeps whatever slack it already had
"maintain-gap"whenever it is not sitting on its linklater and earlierthe successor lands on its earliest legal date, so the gap equals the link's lag

The difference between the two live policies is one clamp. shift-on-overlap throws away a negative correction and only ever pushes forward. maintain-gap applies it, so a successor is pulled back when its predecessor moves earlier.

// src/App.tsx
import { useState } from 'react';
import { ReactGanttChart, type Task } from '@jaeungkim/gantt-chart';
import '@jaeungkim/gantt-chart/style.css';

const initial: Task[] = [
  {
    id: 'design',
    name: 'Design',
    startDate: '2026-03-02T09:00:00Z',
    endDate: '2026-03-06T17:00:00Z',
    parentId: null,
    sequence: '1',
  },
  {
    id: 'build',
    name: 'Build',
    startDate: '2026-03-09T09:00:00Z',
    endDate: '2026-03-20T17:00:00Z',
    parentId: null,
    sequence: '2',
    dependencies: [{ targetId: 'design', type: 'FS' }],
  },
];

export function App() {
  const [tasks, setTasks] = useState<Task[]>(initial);
  return (
    <ReactGanttChart
      tasks={tasks}
      onTasksChange={setTasks}
      schedulingPolicy="shift-on-overlap"
    />
  );
}

Which end of each task a link constrains is the dependency's job, not this page's. The four types and their lag are covered in Dependencies.

When it runs

The engine runs on a bar drag and nowhere else. A move and a left or right resize both go through it. Which successors a resize disturbs depends on the link types, because each type reads one particular end of the predecessor.

Drawing a link never reschedules anything. Neither does deleting one, loading a new tasks array, reordering a row, or turning criticalPath on. A fresh FS link over an overlapping successor leaves that successor overlapping until someone drags a bar.

While the pointer is down the successors move on screen with the bar. Nothing is written during the drag. On release the dragged task and every successor that moved reach onTasksChange together, in one array, as one undo step.

What it never moves

A task with manuallyScheduled: true is skipped. Its dates survive the propagation, and its successors still schedule off those dates, so pinning a task does not cut the chain running through it. The field itself is listed with the rest of the task shape in Task data.

The bar you dragged is also pinned. It lands where the pointer left it even when that breaks its own predecessor link, because the engine only ever walks forward from it. A predecessor is never pushed.

Summary rows are pinned too, whenever hierarchy is on: every id that appears as another task's parentId is skipped, because its dates are rolled up from its children anyway. That roll-up is described in Task list and hierarchy.

No task is reshaped. Propagation moves both ends by the same number of days, so durations and times of day come out of it untouched.

Cycles

A dependency loop is never followed. The graph is sorted topologically, and anything that cannot be ordered is left out of the walk and left at its own dates. The rest of the project still schedules around it.

onSchedulingCycle reports what was skipped:

import { useState } from 'react';
import { ReactGanttChart, type Task } from '@jaeungkim/gantt-chart';

export function Schedule({ initial }: { initial: Task[] }) {
  const [tasks, setTasks] = useState<Task[]>(initial);
  const [stalled, setStalled] = useState<string[]>([]);

  return (
    <>
      {stalled.length > 0 && <p>Not scheduled: {stalled.join(', ')}</p>}
      <ReactGanttChart
        tasks={tasks}
        onTasksChange={setTasks}
        schedulingPolicy="maintain-gap"
        onSchedulingCycle={(taskIds: string[]) => setStalled(taskIds)}
      />
    </>
  );
}

The array is every id that could not be ordered, not only the members of the loop. A task that merely sits downstream of a cycle is listed too, because it could not be ordered either. Those tasks are exactly the ones whose dates the engine did not touch.

Keeping loops out of the data in the first place is what canLink is for; its signature is in Task graph helpers.

[!WARNING] onSchedulingCycle fires many times per gesture: once per preview frame where the drag step changed, once at drop, once at commit. It also never fires while schedulingPolicy is "off", because the graph is not built at all in that case. Use it to set state, not to open a dialog.

The working calendar

workingCalendar is a boolean and defaults to false. On, the chart builds a calendar that skips non-working days and hands it to the scheduling engine, the critical-path pass and the drag's drop snap. Off, those three get a calendar that counts every day, which is plain calendar arithmetic.

import { ReactGanttChart, type Task } from '@jaeungkim/gantt-chart';

export function WorkWeek({ tasks, setTasks }: {
  tasks: Task[];
  setTasks: (next: Task[]) => void;
}) {
  return (
    <ReactGanttChart
      tasks={tasks}
      onTasksChange={setTasks}
      schedulingPolicy="maintain-gap"
      workingCalendar
      holidays={['2026-09-21']}
    />
  );
}

The calendar is built from the same predicate that shades the timeline. Without a custom isNonWorkingDay, a day is non-working when it is a Saturday, a Sunday, or a date listed in holidays, matched as YYYY-MM-DD in UTC. So what is shaded and what is skipped cannot drift apart. The shading itself, and both of those props, belong to The timeline.

isNonWorkingDay replaces that whole check when you pass it. The chart always hands the calendar a predicate, so workingWeekdays — the option a hand-built calendar can set — is unreachable through the component. A work week that is not Monday to Friday has to be written as an isNonWorkingDay function, or built directly with createWorkingCalendar; both are in Working calendar.

What it changes

AreaEffect
Durationduration counts working days rather than calendar days
Laglag: 2 means two working days
Propagationa successor steps over non-working days as it moves
Slackearly and late dates, and both slack numbers, are counted in working days
Drop snappingthe moved edge — the start, for a whole-bar move — snaps forward onto a working day, and the rest of the bar follows by the same days

What it does not change

Bar geometry never sees the calendar. A bar that spans a weekend still spans it on screen — the days do not count. The timeline ticks and the header cells are untouched for the same reason. So is the shading, which has its own prop.

The drag step itself is still calendar-day based. The pointer-to-date conversion counts every day and the calendar only adds the forward snap on top of it, so a move preserves the bar's calendar-day span rather than its working-day span.

That snap is forward-only, and it can be overruled. The minDate / maxDate clamp runs after it and wins, so a bar pinned to a bound can sit on a Saturday. A left-edge resize that would snap past its own end does not snap at all. Those bounds are described in Editing tasks.

With schedulingPolicy="off" and criticalPath off, the drop snap is the only thing workingCalendar changes that you can see.

The critical path

criticalPath is a boolean and defaults to false. On, the chart runs the forward and backward pass over the raw tasks, through the same calendar the scheduling engine uses.

Two things come out of it. In the DOM, a critical class lands on every bar the pass marked critical, on milestones the same way, and on the dependency arrows and arrowheads along the chain. The colours it picks up come from the --gantt-critical family of variables, listed with the rest in Theming. In the data, each transformed task gains a set of read-only fields.

FieldTypeMeaning
earlyStart / earlyFinishstringthe earliest the task can run, as a UTC ISO string
lateStart / lateFinishstringthe latest it can run without moving the project's finish
totalSlacknumberdays it can slip before the project's finish moves
freeSlacknumberdays it can slip before any successor's early start moves
criticalbooleanzero total slack, and not finished
durationnumbercalendar days, or working days when workingCalendar is on

They are undefined while the prop is off, and stay undefined for any task caught in — or downstream of — a cycle, since those tasks are never ordered and so never get metrics. The same numbers come back from computeCriticalPath when you run the pass yourself; its result type is in Critical path.

import {
  ReactGanttChart,
  type GanttColumn,
  type Task,
} from '@jaeungkim/gantt-chart';

const columns: GanttColumn[] = [
  { key: 'name', header: 'Task', width: 220 },
  { key: 'duration', header: 'Days', width: 60, render: (task) => task.duration ?? '-' },
  { key: 'totalSlack', header: 'Slack', width: 60, render: (task) => task.totalSlack ?? '-' },
];

export function Schedule({ tasks, setTasks }: {
  tasks: Task[];
  setTasks: (next: Task[]) => void;
}) {
  return (
    <ReactGanttChart
      tasks={tasks}
      onTasksChange={setTasks}
      criticalPath
      columns={columns}
    />
  );
}

The columns prop is covered in Task list and hierarchy.

Total slack and free slack

totalSlack is measured against the project. It is the number of days the task can slip before the project's finish date moves. A task with zero total slack is on the critical path.

freeSlack is measured against the neighbours. It is the number of days the task can slip before any of its successors has to start later, floored at zero. A task with no successors at all is the exception: its free slack is its total slack, not zero.

A link joins the critical chain only when both of its ends are critical and the link is the one actually holding the successor in place. A slack link between two critical tasks is left out.

Tasks at 100% progress

A finished task is never critical. progress is clamped into 0-100 before the test, so 150 counts as finished. A missing or non-numeric progress does not count as finished.

Its slack numbers do not change. A completed task on the chain keeps totalSlack: 0 and loses only the critical flag. Because a critical link needs both ends, the links either side of it drop off the chain with it, which can leave a visible gap in the highlighted chain. critical: false therefore does not imply totalSlack > 0.

Baselines

A baseline is the plan you want to compare today's dates against. Two fields on the task carry it, both UTC ISO strings:

import type { Task } from '@jaeungkim/gantt-chart';

const audit: Task = {
  id: 'audit',
  name: 'Content audit',
  startDate: '2026-09-01T09:00:00Z',
  endDate: '2026-09-04T17:00:00Z',
  parentId: null,
  sequence: '2',
  baselineStart: '2026-09-01T09:00:00Z',
  baselineEnd: '2026-09-03T17:00:00Z',
};

No prop turns baselines on. Any task carrying baselineStart draws a thin bar under the live one, whatever the scheduling props say. baselineEnd is optional: without it the baseline collapses to a single point one pixel wide.

The baseline element belongs to the row, not to the bar, so dragging the bar slides it across a baseline that stays put. That is the whole point of the feature. The timeline range is widened to cover baseline dates as well, so a baseline that falls outside the live bar is not clipped away.

A milestone gets a small rotated square instead of a bar. The shape is chosen by the task's own type, not by the baseline's dates — a plain task carrying only baselineStart gets the one-pixel bar, not a diamond. Task data owns the milestone rule.

renderBaseline replaces the default element:

import {
  ReactGanttChart,
  type Task,
  type TaskTransformed,
} from '@jaeungkim/gantt-chart';

export function Plan({ tasks, setTasks }: {
  tasks: Task[];
  setTasks: (next: Task[]) => void;
}) {
  return (
    <ReactGanttChart
      tasks={tasks}
      onTasksChange={setTasks}
      renderBaseline={(task: TaskTransformed) => (
        <div
          className="my-baseline"
          style={{ left: `${task.baselineLeft}px`, width: `${task.baselineWidth}px` }}
          title={`Planned: ${task.baselineStart} - ${task.baselineEnd}`}
        />
      )}
    />
  );
}

It is called only for tasks that carry baselineStart, and it receives the transformed task with baselineLeft and baselineWidth already worked out. Absolute positioning stays your job, since the row provides the coordinate space. The default element is aria-hidden="true"; a custom one is not, so give it whatever labelling it needs. The renderer's exact type sits in Renderers.

A worked example

Four tasks, all times UTC.

import type { Task } from '@jaeungkim/gantt-chart';

export const tasks: Task[] = [
  {
    id: 'a', name: 'Kickoff', parentId: null, sequence: '1',
    startDate: '2026-08-31T09:00:00Z', endDate: '2026-08-31T17:00:00Z',
  },
  {
    id: 'b', name: 'Content audit', parentId: null, sequence: '2',
    startDate: '2026-09-01T09:00:00Z', endDate: '2026-09-04T17:00:00Z',
    dependencies: [{ targetId: 'a', type: 'FS' }],
  },
  {
    id: 'c', name: 'Visual design', parentId: null, sequence: '3',
    startDate: '2026-09-01T09:00:00Z', endDate: '2026-09-02T17:00:00Z',
    dependencies: [{ targetId: 'a', type: 'FS' }],
  },
  {
    id: 'd', name: 'Build', parentId: null, sequence: '4',
    startDate: '2026-09-05T09:00:00Z', endDate: '2026-09-09T17:00:00Z',
    dependencies: [
      { targetId: 'b', type: 'FS' },
      { targetId: 'c', type: 'FS', lag: 1 },
    ],
  },
];

Content audit hands straight over to Build, so that link is tight. Visual design finishes a day earlier and its link carries a day of lag, which leaves Build a day of room on that side.

Drag Content audit three days later, to 09-04 09:00 - 09-07 17:00, and drop it:

schedulingPolicyBuild afterwardsWhy
"off"09-05 09:00 - 09-09 17:00unchanged, and now overlapping its predecessor
"shift-on-overlap"09-08 09:00 - 09-12 17:00pushed the three days the broken link demands
"maintain-gap"09-08 09:00 - 09-12 17:00same answer: the link was already tight

Now start over and drag Content audit two days earlier instead, to 08-30 09:00 - 09-02 17:00:

schedulingPolicyBuild afterwardsWhy
"off"09-05 09:00 - 09-09 17:00unchanged
"shift-on-overlap"09-05 09:00 - 09-09 17:00unchanged: nothing is broken, so nothing is pulled back
"maintain-gap"09-04 09:00 - 09-08 17:00pulled back one day, not two

One day, not two, because Build has two predecessors. After the first day the lagged link from Visual design becomes the binding one and stops the pull. Visual design itself never moves in either drag — it is not downstream of the bar you dragged, so the engine never looks at it.

With criticalPath on and no drag, Kickoff, Content audit and Build all report totalSlack: 0 and carry the critical class; Visual design reports totalSlack: 1 and stays grey. Turn workingCalendar on and Build — which runs Saturday to Wednesday — reports duration: 3 instead of 4.

Limits

The engine propagates forward only. It never pushes a predecessor, never resolves a cycle, and never levels the whole project on its own — it starts from the bar you dragged and walks its successors.

It only runs on a bar drag. Everything else that changes dates or links is your responsibility: after importing tasks, drawing a link, or editing a date in a form, the chart's dates are whatever you put in them. scheduleTasks is exported for exactly that case, and can be run over a whole project at once; see scheduleTasks.

Nothing is validated. An endDate before its startDate, an unparseable date string, or two dependencies between the same pair all pass straight through and produce arithmetic on bad input rather than an error.

Every number here is whole days. duration and both slack figures are measured from the start of one date to the start of another, so a task that begins and ends on the same date reports duration: 0 however many hours it covers, and a milestone reports 0 too.

criticalPath never reschedules, and schedulingPolicy never computes slack. They are independent features that happen to share a calendar. The critical path is also computed from each task's own stored dates, so with hierarchy on a summary row's slack and duration can disagree with the span its bar is drawn from.

Baselines are read-only to the chart. It draws baselineStart / baselineEnd and nothing else: snapshotting the plan, storing it, and deciding when to re-baseline are all the host app's job.

There is no editor for anything on this page. lag cannot be changed from the chart, a task cannot be marked manuallyScheduled from the chart, and the working calendar cannot be edited from the chart. All three are data you pass in.

Next: Reordering rows, where moving a row changes the task list rather than the dates.