@jaeungkim/gantt-chart

Critical path

`computeCriticalPath`, `forwardPass`, `backwardPass`

computeCriticalPath runs the critical path method over a Task[] and returns slack numbers, early/late dates and the set of tasks and links that hold the project's finish where it is. forwardPass and backwardPass are its two halves, exported so they can be run on their own. All four, plus the CriticalPathResult and TaskScheduleMetrics types, come from the package root.

import {
  backwardPass,
  computeCriticalPath,
  forwardPass,
  type CriticalPathResult,
  type TaskScheduleMetrics,
} from '@jaeungkim/gantt-chart';

Behaviour and the criticalPath prop live in Scheduling; running the core without React is Headless core.

computeCriticalPath

/** Forward pass, backward pass, and the slack numbers that fall out of the two */
export function computeCriticalPath(
  tasks: Task[],
  options: CriticalPathOptions = {}
): CriticalPathResult
export interface CriticalPathOptions {
  calendar?: WorkingCalendar;
}
OptionTypeDefaultEffect
calendarWorkingCalendarCALENDAR_DAYSThe day unit every number on this page is counted in. CALENDAR_DAYS counts every day; a calendar from createWorkingCalendar counts only working days. See core-calendar.md

The graph is rebuilt with buildTaskGraph(tasks) on every call — there is no memoisation. A task's dependencies array lists its predecessors; link shapes are in core-scheduling.md.

An empty tasks array returns empty metrics, criticalTaskIds and criticalLinkIds, cycle: null and projectFinish: null.

CriticalPathResult

export interface CriticalPathResult {
  metrics: Map<string, TaskScheduleMetrics>;
  criticalTaskIds: Set<string>;
  /** Keys from `linkKey` for the links that lie along the critical path */
  criticalLinkIds: Set<string>;
  /** Ids caught in a dependency cycle - they get no metrics */
  cycle: string[] | null;
  /** The project's earliest finish (UTC ISO string), or null with no tasks */
  projectFinish: string | null;
}
FieldTypeContents
metricsMap<string, TaskScheduleMetrics>Keyed by task id. Only tasks the graph could topologically order get an entry
criticalTaskIdsSet<string>Ids whose critical is true
criticalLinkIdsSet<string>linkKey strings, shape `${predecessorId}>${successorId}:${type}`. A link is added only when both ends are in criticalTaskIds and its own float is exactly 0
cyclestring[] | nullnull when the graph is acyclic. Otherwise every id that could not be ordered — this includes tasks merely downstream of the cycle, not only its members
projectFinishstring | nullThe latest early finish across every task, Date.prototype.toISOString() format (UTC). null only when tasks is empty

TaskScheduleMetrics

export interface TaskScheduleMetrics {
  earlyStart: string;
  earlyFinish: string;
  lateStart: string;
  lateFinish: string;
  /** Days a task can slip before the project's finish moves */
  totalSlack: number;
  /** Days a task can slip before any successor's early start moves */
  freeSlack: number;
  critical: boolean;
  /** Calendar days, or working days when the working-day calendar is on */
  duration: number;
}
FieldTypeUnitMeaning
earlyStartstringUTC ISO stringThe task's own startDate shifted forward by the earliest amount its predecessors allow
earlyFinishstringUTC ISO stringThe task's own end shifted by the same amount
lateStartstringUTC ISO stringThe task's own startDate shifted forward by the latest amount that still leaves projectFinish where it is
lateFinishstringUTC ISO stringThe task's own end shifted by the same amount
totalSlacknumberwhole dayslateShift - earlyShift
freeSlacknumberwhole daysSmallest float across the task's outgoing links, floored at 0; equal to totalSlack when the task has no successors
criticalbooleantotalSlack === 0 and the task's progress is not 100
durationnumberwhole dayscalendar.daysBetween(start, end)

The four date fields are produced by .toISOString(), so they are always UTC with a Z suffix and millisecond precision. Every shift is a whole number of days, so a task's time of day survives both passes unchanged.

totalSlack

How many days the task can start later than earlyStart before projectFinish moves. Computed as lateDates.shift - earlyDates.shift — both shifts being day counts relative to the task's own stored dates.

  • Unit: whole days, in the calendar's day unit. With CALENDAR_DAYS a Friday-to-Monday gap is three days of slack; with a Monday–Friday working calendar it is one.
  • 0 means the task is on the critical chain by date.
  • No clamp is applied, so the value is whatever the subtraction produces.

freeSlack

How many days the task can start later than earlyStart before it pushes the earlyStart of a successor.

  • For a task with at least one outgoing link: Math.max(0, Math.min(...floats of its outgoing links)). The floor at 0 means this field is never negative for such a task.
  • For a task with no outgoing links it is set to totalSlack, not 0. A leaf task's two slack numbers are therefore always equal.
  • Unit: whole days, in the same calendar unit as totalSlack.
  • Per-link float is calendar.daysUpTo(predecessorAnchor, successorEarlyAnchor) - link.lag - predecessorEarlyShift, so a link's lag is subtracted in the calendar's day unit too.

freeSlack <= totalSlack for any task with successors.

forwardPass

/**
 * Earliest each task can run given its predecessors, walked predecessors-first.
 * A task with no predecessor stays on its own dates.
 */
export function forwardPass(
  tasks: Task[],
  calendar: WorkingCalendar = CALENDAR_DAYS,
  graph: TaskGraph = buildTaskGraph(tasks)
): Map<string, EarlyDates>
export interface EarlyDates {
  start: Dayjs;
  finish: Dayjs;
  /** Days later than the task's own dates */
  shift: number;
}

shift starts at 0 and only ever grows, so a task is never pulled earlier than its own startDate. Tasks left out of graph.order are added to the returned map at their own dates with shift: 0, so the map covers every id in tasks.

backwardPass

/**
 * Latest each task can run without moving the project's finish, walked successors-first.
 *
 * Takes the forward pass's output rather than recomputing it, so it can be exercised on
 * its own with hand-written early dates.
 */
export function backwardPass(
  tasks: Task[],
  early: Map<string, EarlyDates>,
  calendar: WorkingCalendar = CALENDAR_DAYS,
  graph: TaskGraph = buildTaskGraph(tasks),
  projectFinish?: Dayjs
): Map<string, LateDates>
export interface LateDates {
  start: Dayjs;
  finish: Dayjs;
  /** Days later than the task's own dates the task could still run */
  shift: number;
}
ParameterRequiredDefault
tasksyes
earlyyes
calendarnoCALENDAR_DAYS
graphnobuildTaskGraph(tasks) — rebuilt unless the caller passes the same graph the forward pass used
projectFinishnoThe latest finish in early

With no projectFinish argument and an empty early map, the function returns an empty map. Unlike forwardPass, the returned map covers only the ids in graph.order.

Not exported from the package root

These names appear above but are not in src/index.ts, so they cannot be imported from @jaeungkim/gantt-chart:

NameKindWorkaround
EarlyDatestypetype Early = ReturnType<typeof forwardPass> gives Map<string, EarlyDates>
LateDatestypetype Late = ReturnType<typeof backwardPass>
CriticalPathOptionstypePass the object literal inline; calendar is its only member
normalizeProgressfunctiontypeof p === 'number' && !Number.isNaN(p) ? Math.min(100, Math.max(0, p)) : null — the real one returns null, not a number, for a missing or NaN progress
taskStart, taskEnd, linkSourceDate, linkTargetDatefunctionsInternal; no public equivalent

buildTaskGraph, linkKey and TaskGraph are exported — see core-graph.md. CALENDAR_DAYS, createWorkingCalendar and WorkingCalendar are exported too — see core-calendar.md.

Notes

A task whose progress is 100 is never marked critical. critical is totalSlack === 0 && normalizeProgress(task.progress) !== 100, and normalizeProgress clamps to the 0100 range first, so progress: 150 counts as 100 and drops the task off the critical path. A non-numeric or NaN progress is not treated as finished.

The 100%-progress rule changes the flags only. totalSlack and freeSlack for a finished task keep the values the two passes produced, so critical: false does not imply totalSlack > 0. Because a critical link needs both ends in criticalTaskIds, marking a task finished also removes every link touching it from criticalLinkIds.

Tasks caught in a dependency cycle, and tasks downstream of one, get no entry in metrics — the metrics loop walks graph.order, which excludes them. Their ids appear in cycle.

duration is day-granular. calendar.daysBetween takes startOf('day') on both ends, so a task running 09:00 to 17:00 on one date reports 0. A milestone reports 0 because its end is its startDate.

projectFinish reduces over every entry in the forward pass's map, which includes tasks left out of graph.order. A task caught in a cycle can therefore set the project finish even though it has no metrics.

linkKey does not include lag. Two dependencies between the same pair with the same type share one key, so they share one float value and one criticalLinkIds entry.

computeCriticalPath never moves a task. It reads tasks and returns numbers; propagation is scheduleTasks (core-scheduling.md).